NeuRizer’s March-quarter Activities Report provided an update on the early implementation of the Reliance arrangements announced in March.
The company reported that payment under the Reliance arrangements had commenced in April 2026, with the April payment received. NeuRizer also hosted representatives from Reliance’s engineering team and consultants at Leigh Creek so they could inspect and understand the demonstration plant ahead of its planned disassembly and transport to India.
At Leigh Creek, NeuRizer continued groundwater monitoring, maintenance, environmental management and regulatory work. The company also continued progressing the Stage 1 Environmental Impact Statement, with submission planned for May at the time of the announcement.
NeuRizer’s securities remained suspended from quotation. The company reported that several overdue quarterly reports had been lodged on 30 March, while work continued on the outstanding 2025 full-year accounts and Annual Report.
The accompanying Appendix 5B also stated that Reliance invoices issued and paid in April provided funding for the following two quarters, with ongoing monthly payments expected over the following 15 months.
Read the full ASX announcement below
This summary is provided for convenience only. Readers should refer to the original ASX announcement for the complete information and context.